Third phase of beach nourishment project could go to bid by Thursday

The yellow numbers and arrows indicate the areas and amounts of sand in cubic yards planned for nourishment of Emerald Isle beaches. At the top are geographic descriptions of the areas. (Carteret County Shore Protection Office graphic)

EMERALD ISLE — It’s been about two months since the last Bogue Banks beach nourishment project ended April 29, but Carteret County officials are moving to go out for bids for the third phase of what’s known as the post-Hurricane Florence project.

Greg Rudolph, manager of the County Shore Protection Office, said Thursday he hopes to release the bid document for the project to potential contractors Thursday and have a bid opening by Thursday, July 30.

If the county gets bids from three companies, they can be opened that day, but if there are fewer bids, the project will have to be readvertised for a week.

“Our (engineering) team at Moffatt & Nichol is furiously preparing the plans and contract documents,” Mr. Rudolph said. “The bid solicitation schedule isn’t quite set in concrete yet,” but the idea is to get the bid documents out and award a contract as soon as possible, as that generally results in lower bids and a more favorable contract.

The phase three project is to include the last stretch of western Emerald Isle. Most of western Emerald Isle was included in the project that wrapped up April 29.

In addition, Mr. Rudolph said, the project is to include central Emerald Isle, which has not had its beaches nourished in years, and maybe a small portion of eastern Emerald Isle nourished in 2019 but considered a “hot spot” for erosion.

Without going into detail, Mr. Rudolph said engineers at Moffatt & Nichol are “exploring different beach-fill geometries” for eastern Emerald Isle in an effort to find a way to address the hot spot.

“We have a great opportunity here to try something different than the continuous berm-width that is commonly used,” he said.

Mr. Rudolph has estimated phase three could cost as much as $45 million.

Although the length of beach to be covered and the amount of sand to be discharged is similar to the $28.2-million phase two, it’s farther away from the sand dredge site off Atlantic Beach, so it costs more to move the material.

The project is to begin late this year or early in 2021.

Phase one covered almost all of Salter Path, all of Indian Beach and eastern Emerald Isle. It was completed in 2019 and cost $20.2 million. Phase two covered western Atlantic Beach, all of Pine Knoll Shores, the remainder of Salter Path and a portion of western Emerald Isle.

 

Contact Brad Rich at 252-864-1532; email Brad@thenewstimes.com; or follow on Twitter @brichccnt.

(0) comments

Welcome to the discussion.

As a privately owned web site, we reserve the right to edit or remove comments that contain spam, advertising, vulgarity, threats of violence, racism, anti-Semitism, or personal/abusive/condescending attacks on other users or goading them. The same applies to trolling, the use of multiple aliases, or just generally being a jerk. Enforcement of this policy is at the sole discretion of the site administrators and repeat offenders may be blocked or permanently banned without warning.