New equipment improves FRC East support of V-22 component

William Touchette, a pneudraulics system mechanic at Fleet Readiness Center East, secures a connection between a V-22 Osprey swashplate actuator and a new test stand before running acceptance testing procedures on the component. The new test stand will allow FRC East to improve support of the critical component by reducing testing time and delivering functional actuators to the fleet more quickly and directly. (Contributed photo)

By Heather Wilburn, Fleet Readiness Center East

CHERRY POINT — New test equipment at Fleet Readiness Center East has positioned the facility to help alleviate one of the top degraders to V-22 Osprey readiness.

The new test stand, which checks the functionality of the V-22 swashplate actuator, cuts testing time in half to produce “ready for issue” components for the supply chain. The swashplate actuator is a flight-critical control that guides the aircraft’s rotors. With the component’s presence on the V-22 degrader list, every day it is in process counts.

“Getting this bench here into production has been high on my priority list, and it’s already making a difference in our throughput,” FRC East Commanding Officer Capt. Mark Nieto said. “Now we have the equipment; if we can overcome challenges in the supply chain, I know our artisans can do even more.”

The swashplate actuator’s position on the degraders list drove the push to stand up the new test system at FRC East, said John Hinson, head of the Maintenance, Repair and Overhaul Engineering Test Equipment Engineering branch. The legacy test stand – the V-22 hydraulic actuator test stand, or VHATS – doesn’t allow FRC East to declare ready for issue status on the tested swashplate actuators. Actuators that passed testing at FRC East have to be sent to Moog, the component’s original equipment manufacturer, in order to receive the RFI declaration.

A public-private partnership with Moog will change this process.

“One of the big benefits of this test stand is that Moog, the company that built this stand, is also the OEM for the swashplate actuator and will be using this exact same stand,” Mr. Hinson said. “We’ll be testing on the exact same test stand, running the exact same software as the component OEM.”

Using the same setup will eliminate any discrepancy in test results and should allow for much easier comparison, Mr. Hinson added. 

“As far as testing consistency and ensuring we’re testing exactly how the OEM is testing; there’s no question there,” he said. “The fact that we were working with the component OEM gave us a better product in the end.”

In addition to improved accuracy, the new stand also mitigates concerns regarding throughput and capacity. The new stand produces time savings in the testing itself and, because it tests the V-22’s flaperon and elevator actuators, also manufactured by Moog, it frees up the VHATS system for testing other components.

“This test stand is very good for the V-22 platform,” explained Travis Lowe, components program manager in MRO Logistics at FRC East. “It lowers our run time for testing in half, allowing the depot to have more throughput on swashplate actuators. It also takes the workload off the VHATS stand so we can increase throughput on other V-22 valves and actuators.”

William Touchette, a pneudraulics system mechanic at FRC East, said he has seen the test time reduced by almost half. Acceptance testing procedures, which took a minimum of six hours on VHATS, and sometimes longer, can now routinely be completed in under three and a half hours.

“Running the actuators on VHATS, I could maybe get one tested out in an eight-hour period, if it was good,” he said. “Now I can take two and test them out in that same eight-hour period. If we have the parts and can build them, that’s almost doubling our output.”

Getting the test stand operational at FRC East required an all-hands effort, with players from across the board. While processes ranged from procurement to installation to calibration, and challenges including the coronavirus pandemic sometimes made for slow progress, the goal remained steady: make a difference in naval aviation readiness.

“Everyone on this team here – facilities, production, engineering and the Fleet Support Team – did a great job getting it set up and running,” Capt. Nieto said. “They had to jump over a lot of hurdles to get to where they’re at, and they did it. I’m really proud of them.”

(0) comments

Welcome to the discussion.

As a privately owned web site, we reserve the right to edit or remove comments that contain spam, advertising, vulgarity, threats of violence, racism, anti-Semitism, or personal/abusive/condescending attacks on other users or goading them. The same applies to trolling, the use of multiple aliases, or just generally being a jerk. Enforcement of this policy is at the sole discretion of the site administrators and repeat offenders may be blocked or permanently banned without warning.